MEPCO Completes 112 LT Schemes In Sept
MULTAN, (Muzaffargarh.City – 31st Oct, 2018 ) ::Multan Electric Power Company (MEPCO) has completed 112 low tension (LT) schemes during September 2018 to provide new connections and upgradation of the system.
According to a press release issued here on Wednesday, the schemes have been completed with a cost of over Rs 78.4 million.
MEPCO completed 16 LT schemes in Multan circle with a cost of Rs 11.
3 millions, 20 schemes in Muzaffargarh circle with a cost of Rs 11 million, 17 in Rahim Yar Khan circle with a cost of Rs 19.2 million, 20 schemes in DG Khan with a cost of Rs 9.8 million, 10 schemes in Sahiwal circle with Rs 8.7 million, 15 schemes in Bahawalpur circle at a cost of over Rs 9.9 million, six schemes in Khanewal circle with a cost of Rs 3.5 million, seven schemes in Vehari circle with a cost of Rs 5.3 million while Rs 514,000 were spent on one scheme in Bahawal Nagar circle during last month.